SpecTopics: Using the DORA Directory with ASCE 7 Calculations

The Directory of Roof Assemblies (DORA) is the newest listing program for International Building Code (IBC) Chapter 15-compliant roofing assemblies. This web-based directory is free to use and is available to any user, including specifiers, architects, consultants, building owners, contractors, and manufacturers. DORA provides listings for assemblies in accordance with wind uplift designs. You can search for tested assemblies by uplift requirements as determined by ASCE 7 calculations if desired.

To meet the IBC-required uplift pressures associated with the roofing assemblies, uplift pressures must be calculated in pounds per square foot (psf) and verified by testing.

The determination of the uplift should be completed by the designer of record or through his/her licensed engineer using ASCE 7. Once accomplished, manufacturers can confirm the assembly's compliance through uplift rating records.

The use of ASCE 7 is based on the adoption of the IBC, either statewide or locally.

IBC edition ASCE 7 edition
2018 and 2021 2016
2012 and 2015 2010
2003, 2006, and 2009 2002-2005

Once these pressures have been determined, it must be certified that the specified roof assembly has been tested following ANSI/FM 4474 in psf. These records are then listed on the DORA website.

Process Summary
It's simple to determine the correct roofing assembly for a specific building to meet the IBC:
1. Determine the building's uplift pressure using the ASCE 7 calculations, which should be completed by a locally licensed or qualified design professional.
2. Review the roofing assembly's "reported pressure", which is collected from manufacturers' results and ratings from ANSI/FM 4474 and listed on the DORA website.
3. Compare and verify the DORA listed pressures, which need to be equal to or greater than the ASCE 7 pressures.

Once the assembly has been selected and confirmed to meet the uplift pressures, it's important to read and carefully consider warranties to confirm that the wind coverage meets the building owner's needs and is easy to understand.

Keep in mind, when higher wind speed coverage is requested from the material manufacturer, additional enhancements may be necessary to qualify for the warranty, which will likely increase the cost of the total assembly and may increase the cost of the warranty.

To learn more about the DORA Directory, visit DORA's website.

If you have any questions regarding ASCE 7 or the DORA Directory, please contact Brian Chamberlain.

Up Next

February 09, 2022

SpecTips: Achieving Sustainability Credits with Roof Garden Systems

When choosing building products and systems, it is important to take a holistic approach and consider all aspects of sustainability, including the manufacturing process, long-term performance, environmental benefits, energy savings, and resiliency. In the roofing industry, there is no system that checks all the sustainability boxes better than a Roof Garden.

January 26, 2022

SpecTopics: Wind Design for Rooftop Overburden Systems

Over the past several decades, the use of green roofing and rooftop amenity space products has been on the rise due to their environmental benefits and ability to maximize a building’s useable space while staying within its existing footprint. The influx of rooftop overburden installations has led to an increase in questions surrounding proper wind design to avoid overburden material blow-off and to meet building code and insurance requirements.

January 12, 2022

SpecTips: A Sustainable Solution to Very Severe Hail Requirements

FM Global, an international insurer of commercial buildings, has traditionally recommended that its insured building owners in areas of the country which receive frequent hail damage use Property Loss Prevention Data Sheet FM 1-34, “Hail Damage”.