Installation Tips: Don't Let Cold Weather Stall Your Project
January 8, 2019

Cold-weather installations can be challenging and may require extra time and labor. Check out these storage and installation tips to help your winter projects run more smoothly.


Storage Tips

Low-VOC adhesives and primers and pressure-sensitive (PS) accessories
  • Store between 60°F-80°F. If stored below 60°F, restore to between 60°F-80°F before application. If adhesive is stored in below-freezing temperatures, it may solidify in the can. If this occurs, restore to room temperature for at least 24 hours before using. 
  • Water-based adhesives (HydroBond™, Aqua Base 120) will freeze in temperatures below 32°F and will be unusable thereafter. 
  • On winter jobsites, a heated enclosure or hot box is essential to ensure that adhesives and PS products maintain their intended properties and ease of application. Visit powerblanket.com for more information on jobsite heating equipment. 

Application Tips

Low-VOC Bonding Adhesive and EPDM x-23 Low-VOC Bonding Adhesive
  • Allow membranes to relax for at least 30 minutes before installing. 
  • Avoid puddles and globs, and re-roll any wet areas to break the skin and allow solvents to flash off. 
  • Shaded roof areas take longer to flash off than sunny areas. 
  • Use the “tack test” to ensure that solvents have flashed off and the adhesive is still tacky. 
  • If the adhesive is not tacky, it has over-dried and must be re-applied at the published coverage rate.
  • Install the membrane shortly after adhesive passes the tack test, then immediately broom or roll the membrane after setting the sheet. 
PS EPDM flashings
  • In cold temperatures, a heat gun must be used to warm PS flashings until warm to the touch prior to installation. This will make application much quicker and easier. 

TPO membranes
  • Test weld in the morning and then again after lunch when the temperature has likely increased. 
  • The speed of the Automatic Heat Welder may need to be adjusted to produce proper seams. 

FAST and Flexible FAST
  • Keep your materials warm. FAST in drums must be a minimum of 70°F for the material to flow and mix properly. Storing FAST drums outside overnight in cold temperatures can cause the adhesive to freeze. FAST Bag in a Box and FAST Dual Cartridges should be stored in a hot box on the roof.

For more information about building codes, please contact your local sales representative.

October 1, 2019
Special Color TPO Accessories

As the demand for different colored roof membranes has grown, Carlisle introduced its TPO Color Palette with five new colors. In addition to standard white, gray, and tan, Carlisle’s TPO Color Palette now features Rock Brown, Slate Gray, Terra Cotta, Patina Green, and Medium Bronze. Projects that use special color membrane from the TPO Color Palette usually need flashings and accessories in the same color. Here, contractors have two choices, one of which is painting standard accessories to match the membrane. However, this is a great opportunity to use Carlisle’s custom TPO accessory program and avoid painting altogether. All Carlisle custom accessories are available in the five TPO Color Palette colors, as well as white, tan, and gray. Whether it’s a simple split pipe seal or a complex prefabricated curb wrap, Carlisle can make it in all eight TPO colors and get it to the job quickly. In addition to being available in eight colors, here are some other great advantages to using custom flashings from Carlisle: • Save time vs. field fabrication: Trying to field-fabricate flashings can be time-consuming work, even for the most skilled and experienced roofers. Using prefabricated flashings saves time. • No need for paint: There’s no need to prime and paint the accessories to match the membrane; just install and go. • Speed: Custom accessories can be fabricated and shipped within days, not weeks. • Quality: All of Carlisle’s custom TPO accessories carry the Certified Fabricated Accessory (CFA) stamp of approval, indicating they are eligible for coverage as part of the Carlisle Total Roofing System Warranty. Next time you have a project using Carlisle’s TPO Color Palette TPO, consider using custom accessories to make the job faster and easier to install. Sure-Weld TPO Special Color Painting Guide  Sure-Weld TPO Special Color Program  Custom Accessory Quote Request Form      Adam Burzynski     TPO Product Manager     Product Marketing     [email protected]

Read This Post
September 17, 2019
Solving Unique Challenges with a Hybrid Approach to Insulation

One of the simplest ways to meet building codes requirements in construction is through the effective use of insulation. There are several types of rooftop insulations available in the marketplace, but two of the most commonly accepted in commercial roofing applications are polyisocyanurate (polyiso) and expanded polystyrene (EPS). Polyiso is a lightweight and cost-effective, closed-cell, rigid foam board insulation that provides energy-efficient solutions for buildings in any region and climate, as well as outstanding return on investment and significant energy savings. EPS is a closed-cell, rigid foam insulation manufactured using expandable polystyrene. It is block-molded for most construction applications and is highly customizable, enabling thicknesses up to 40 inches in a single board. EPS is versatile and durable and can provide significant cost and labor advantages. Both polyiso and EPS provide great benefits and R-value in roof construction projects. However, projects often arise when a hybrid solution to insulation may be the most practical. A hybrid polyiso/EPS solution can help you edge out the competition in a number of scenarios. New Construction with Concrete Decks  A recent innovation introduced by Carlisle is ChannelDry® EPS Insulation. ChannelDry is ideal for new construction projects with structural concrete, lightweight structural concrete, and lightweight insulating concrete roof decks. Using ChannelDry in conjunction with one-way and two-way relief vents allows the installation of the roof system to begin upon structural cure of concrete (typically around 28 days). ChannelDry is compatible with ballasted, mechanically fastened, induction welded, and adhered single-ply roofing systems. The use of ChannelDry creates a problem-solving solution for new construction involving concrete decks, enabling construction to commence immediately upon structural cure. Standing Seam Metal Roofs  With square-, taper-, and profile-cut flute-fill products in custom shapes and sizes, a solution is available for all metal retrofit roofs. Combining EPS to fill the metal roof flutes with a subsequent layer of insulation or coverboard can create an ideal foundation for a retrofit roof. Click here to hear a contractor describe the benefits of this system from a project in Windsor, Ontario, Canada. Tapered Roof Design  A tapered roof is another ideal candidate for a hybrid approach to save time and money. With thicknesses up to 40" and virtually any slope available in a single board, a base layer of tapered EPS insulation can save nearly 30% in product cost alone, with additional savings on installation time when combined with polyiso. Combining polyiso and EPS in commercial roofing applications is an effective solution that can often save you money and labor on a project. Contact your local Carlisle representative to learn more.

Read This Post
September 3, 2019
Roofing with Resilience: A Review of 30-Year EPDM Enhancements

The history of EPDM roofing runs deep. With over 50 years on the market and billions of square feet produced and installed, Carlisle SynTec’s EPDM has a proven track record as one of the most resilient membranes in the single-ply roofing industry today. As time goes on and the construction industry evolves, more sustainable structures are becoming the norm. Building codes are increasingly robust and are placing a greater emphasis on protecting your building from Mother Nature’s wrath. Your roof system plays a huge part in achieving compliance and serves as the first line of defense against hail, wind, and other damaging elements. This is where EPDM’s sustainability and durability come into to play. Sustainability and resiliency are some of the strongest attributes of Carlisle’s EPDM membranes, and EPDM’s durability allows us to offer a high-end, 30-year Total System Warranty that guarantees long-term performance. Below are the enhancements that Carlisle SynTec requires when upgrading to a 30-year EPDM system: 30-Year EPDM Enhancements The Membrane: The thicker and more durable 90-mil EPDM, 75-mil reinforced EPDM, or 145-mil FleeceBACK® EPDM are required; fully adhered, mechanically fastened, or ballasted designs are available. The thicker membranes will provide greater long-term performance and superior resistance to weathering. Please note, 45-mil and 60-mil membranes are not eligible for 30-year Total System Warranties. The Splices: Membrane splices are one of most important parts of any roofing system and utilizing our Factory-Applied Tape™ means more watertight seams and fewer warranty claims. On a 30-year EPDM system, Carlisle requires membrane with 6”-wide Factory-Applied Tape or 6” SecurTAPE™ to be installed at all seams and end laps. The 6”-wide tape has greater peel and sheer strength and results in a stronger bond. Please note, 3” factory-applied or hand-applied tape on 30-year warranties must be stripped in with Pressure-Sensitive Cured Cover Strip. The Flashing Details: In addition to seams, flashing details are critical to preventing issues where rooftop penetrations are tied in to the field membrane. On 30-year EPDM systems, Carlisle requires specific details to be double-wrapped or covered with two layers of flashing. Below is a list of these details: Key U = Universal (applies to all 30-year systems) A = Adhered Systems Only B = Ballasted Systems Only MF = Mechanically Fastened Systems Only U-2D SecurTAPE Splice Intersection (25-/30-Year Warranties) U-8A.1 Pre-Molded Pressure-Sensitive Pipe Seal with 90-mil Membrane or 25-/30-Year Warranties U-8B.1 Field Fabricated Pipe/Structural Steel Tube Flashing for 25-/30-Year Warranties U-15D.1 Inside Corner Flashing for Projects with 90-mil Membrane or 25-/30-Year Warranties U-15H Outside Corner Flashing for Projects with 90-mil Membrane or 25-/30-Year Warranties A-2 Membrane Splice (25-/30-Year Warranties) B-2 Membrane Splice (25-/30-Year Warranties) MF-2D Membrane Splice (25-/30-Year Warranties) MF-2E SecurTAPE Splice Intersection (25-/30-Year Warranties) ***Please speak with a Carlisle SynTec Design Analyst about additional 30-year requirements in regards to adhesives, coverboards, insulation, fastening density, perimeter securement, and metal edging.***     Ryan Ferguson     EPDM Product Specialist     Product Marketing     [email protected]

Read This Post
X
Email to your Colleagues >
Separate multiple emails with a comma or semicolon.
Copy Me


Please log in to share this item by email.
Add to a Collection >
Please log in to share this item to your collections.
Private
Private Collection (change)

Loading...
Invite user by email:
User Invited. Invite another
User Invite Failed, try again.
X
Visibility Options
Public Collection
Anyone with a link can view. No sign-in required.
Private Collection
Only people explictly granted permission can access. Sign-in required.
X

You are now working in your copied collection
Okay